A request has been received from Parkway Construction(MK) Ltd.for a temporary road closure to apply to a section of B4030 Middleton Stoney Road, whilst essential road improvement works are carried out.
A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 27 January 2020 up to and including 14 February 2020. This is a 24 hour per day closure.
(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)
Notice of intention to make the Order will be published in the local press.
A copy of the drawing showing the extent of the closure and also the alternative route for traffic is attached.
Further information regarding the works may be obtained by contacting Matthew Vicarage of Parkway Construction (MK) Ltd on 01908 395000 , mobile 07834 518872 or email matt@parkwaymk.com
T7327 / RAG
Regards,
Robert Graham
Officer
Network Management
Communities
Oxfordshire County Council
Please see the below in reference to the above:
Notice of Order – Chesterton, B4030 Middleton Stoney Road
Last Updated 23 July 2020