A new crossing installation and bridge demolition will be taking place over two weekends in July 2021.
The A4421 will be closed during these works and the diversion route will include the A421. A43 and B4100.
Friday 9th July – Monday 12th July
The A4421 will be closed at Finmere Bridge from Friday 9th July 8:00pm until 6.00am on Monday 12th July. The road will be closed to traffic to ensure the safe demolition of Finmere Bridge.
We have put in place contingency dates for the demolition in case of significant issues such as adverse weather.
New crossing installation
Friday 23rd July – Monday 26th July
The A4421 will be closed at Finmere Bridge from Friday 23rd July 8.00pm until 6.00am on Monday 26th July. The road will be closed for the installation of the new temporary bridge, which will carry our haul road and access road over the A4421.
Contingency dates if installation cannot take place from the 23rd – 26th July as planned
Friday 6th August 8.00pm to 6.00am Monday 9th August.
If you have any queries on this please contact the HS2 Help desk 08081 434 434


Last Updated 8 July 2021